Pursuant to Section 109.6 of the IBC and Section R108.5 of the IRC the Building Official will authorize refunds, payable to the original payee, as follows:

(1) Permit/application inactivity after one year will result in forfeiture of all fees.

(2) For project withdrawal within one year of date of submission with only data entry, the refund shall be 80 percent.

(3) Plan review fees will be forfeited if a plan review was conducted.

(4) If after a permit is issued and a request to withdraw from the project is received within one year of the date of issuance and no work has been started, the refund shall be 80 percent.

(5) All other fees paid to other divisions will be refunded at their respective division’s discretion.

(6) A submittal of the calculated fees shall be reviewed and approved by the Building Official prior to dispersal.