31.07.190 Summary of City of Forks Capital Improvement Plan.
(1) Description of Table 11. Appendix “B” is the City of Forks Capital Improvements Plan. This provides a brief description of each of the capital improvement projects agreed upon in the March 1993 capital facility plan, provides the justification for the project, and provides an estimate of the total project costs. Table 11 is a summary of the Capital Improvement Plan, divided by department or area of concern.
Water Systems |
|||||||
Fund Source |
1993 |
1994 |
1995 |
1996 |
1997 |
1998 |
|
Water Line Extension |
5 |
700,000 |
|||||
Thomas Addition Extension |
3 |
55,000 |
|||||
Water Tanks |
3 |
10,000 |
|||||
Subtotals |
700,000 |
10,000 |
55,000 |
||||
Sewer |
|||||||
Fund Source |
1993 |
1994 |
1995 |
1996 |
1997 |
1998 |
|
Sewer Plan Update |
3 |
10,000 |
|||||
Subtotals |
10,000 |
||||||
Streets/Drainage |
|||||||
Fund Source |
1993 |
1994 |
1995 |
1996 |
1997 |
1998 |
|
Comprehensive Drainage Plan |
3 & 5 |
50,000 |
|||||
Forks Industrial Park Roadway |
5 |
210,000 |
|||||
Bogachiel Way /Calawah Way |
2 |
1,560,000 |
|||||
SR 101 |
2 & 4 |
420,000 |
|||||
Sixth Ave. |
2 |
5,000 |
|||||
3rd Ave. S.E. |
2 |
5,000 |
|||||
Russell Rd. |
2 |
3,000 |
|||||
Gateway Landscaping |
5 |
20,000 |
|||||
Subtotals |
1,790,000 |
470,000 |
5,000 |
5,000 |
5,000 |
||
Building/Grounds |
|||||||
Fund Source |
1993 |
1994 |
1995 |
1996 |
1997 |
1998 |
|
City Hall |
2 |
20,000 |
|||||
Water Compound |
3 |
20,000 |
|||||
Forks Industrial Park Site Development and Buildings |
5 & 1 |
1,414,200 |
|||||
Subtotals |
20,000 |
1,414,200 |
20,000 |
||||
Parks and Recreation |
|||||||
Fund Source |
1993 |
1994 |
1995 |
1996 |
1997 |
1998 |
|
Calawah River Access |
3 & 5 |
300,000 |
|||||
Aquatic Center |
5 & 6 |
4,000,000 |
|||||
Subtotals |
300,000 |
4,000,000 |
|||||
Airport |
|||||||
Fund Source |
1993 |
1994 |
1995 |
1996 |
1997 |
1998 |
|
Airport Plan Update |
5 |
30,000 |
|||||
Subtotals |
30,000 |
||||||
Grand Totals |
|||||||
1993 |
1994 |
1995 |
1996 |
1997 |
1998 |
||
Annual Totals |
20,000 |
4,234,200 |
510,000 |
60,000 |
4,005,000 |
3,000 |
|
Funding Sources: 1. General Fund 2. Dedicated Funds 3. Enterprise Funds 4. Improvement District 5. Grants 6. Bonds 7. Other |
(2) Prioritization of Projected Needs. The identified capital improvement needs listed in Appendix “B” were developed by the City department heads. The following criteria were applied informally in developing the final listing of proposed projects.
Economic Considerations:
•Potential for Financing
•Timeliness of Opportunity
•Benefit to Economy and Tax Base
Service Considerations:
•Safety, Health, and Welfare Factors
•Effect on Quality of Service
Feasibility Considerations:
•Legal Mandates
•Citizen Support
Consistency Considerations:
•Linkage to Other Planned Projects
Cost Estimates for Projected Needs: Cost estimates in this element are presented in 1993 dollars and were derived from past experience in constructing capital projects.